Cross Island MRT Line: LTA delays environment study

$
0
0

SINGAPORE - The Land Transport Authority (LTA) will hold back its study of the environmental impact of the Cross Island MRT Line until after nature groups have completed their investigations.

It made the decision after its officials met nine representatives of several nature groups yesterday. The meeting was the first face-to-face session between the LTA and the groups since they expressed concern about the proposed MRT line passing through the Central Catchment Nature Reserve.

The groups, which include the Nature Society Singapore and Raffles Museum of Biodiversity Research, offered to conduct a study on how different alignments of the line would impact flora and fauna in the nature reserve.

In accepting it, LTA chief executive Chew Hock Yong said the authority will consider the findings before deciding how to conduct its own environmental impact assessment.

Preliminary plans have an estimated 1.4km of the line passing underground through the reserve. Several groups had expressed concern that even soil investigations for the line would damage the nature reserve's ecosystem, and called for the line to go around the reserve instead of through it.

Mr Chew said the nature groups' study will help the LTA avoid undue impact on the environment. "We will not start any work until such time where there is a proper understanding of what is the correct way to do it, so as to minimise the impact on the nature reserve," he said.

He noted that plans presented in January were a "broad brush stroke", and the LTA will consider several factors before it decides on an alignment.

This includes environmental impact, overall travel time, how the line fits into the land use plan and whether it will affect any existing house.

Engineering studies are also needed to decide if it is technically feasible to have the line skirt around the reserve.

Mr Tony O'Dempsey, the Nature Society's spokesman on the issue, said the meeting was positive and the study should take about six months.

Mr Chew said the LTA had intended to call a tender for environment studies late this year or early next year. Plans for the line remain on track even though the LTA is waiting for the study to be completed, he added. The line will run from Changi to Jurong, and is slated for completion in 2030.